E.ON and Evonik ensure Marl Chemical Park’s energy supply
To ensure the energy supply to Marl Chemical Park, Evonik’s largest production facility, contracts were signed yesterday to build a new combined-cycle gas turbine (CCGT) power plant. The plant is a joint project of Evonik and E.ON. Siemens will supply the CCGT.
Marl Chemical Park currently receives electricity and steam from three power plants consisting of a total of five generating units. The oldest of these is unit 3, which in a few years will reach the end of its useful operating life. Unit 3 will be replaced with a new CCGT plant with 60 megawatts (MW) of electric capacity. E.ON will build the new plant at a central location at Evonik’s production facility; the plant is expected to enter service in 2015. Switching from coal to gas will enable Evonik to reduce its carbon emissions at Marl by about 280,000 metric tons annually.
Evonik will control and have operational and legal responsibility for the power plant once it is in service. E.ON will plan, finance, and build the new Marl plant and provide a number of services related to its operation. E.ON Energy Projects, the E.ON subsidiary that will build the plant, has installed, or played a key role in installing, 1,600 MW of electric capacity.
"The new CCGT will be an important step toward updating Marl Chemicals Park’s power and steam supply," said Caspar Gammelin, President Site Services at Evonik. "In view of E.ON’s well-earned reputation for new-build expertise, we’re pleased to have them as a partner in our joint project." The new plant will ensure that Marl Chemical Park has a reliable and cost-effective supply of power and heat well into the future.
"The construction of a new CCGT at Marl Chemical Park is another example of how E.ON is systematically propelling the expansion of distributed generation in Germany and doing so in a customer-oriented manner," said Ingo Luge, CEO of E.ON Deutschland. He added that "distributed generation is an important aspect of the transformation of Germany’s energy system, to which we intend to make a substantial contribution."
"For Siemens, receiving the order to supply key components to the new Marl power plant is confirmation that we’re able to provide our customers with sustainable products to update their energy supply," said Markus Tacke, CEO of Siemens Energy’s Industrial Power business unit. "Combining an SGT-800 gas turbine and an SST-300 steam turbine is a proven solution. Together they create a state-of-the-art CCGT that optimally meets today’s requirements for operational flexibility and reliable performance over the long term. The gas turbine generates electricity extremely efficiently and economically." Siemens was also awarded a multi-year service contract to maintain the gas turbine and ensure that it meets high standards for performance, availability, and reliability.
Latest news
MOL inaugurated €1.3 billion polyol complex in Tiszaújváros, Hungary
The €1.3 billion project is MOL's largest organic investment to date, for which it has also received support from the Hungarian state. Thanks to technology of thyssenkrupp Uhde and Evonik, the plan...
Arkema and ProLogium enter cooperation for next-generation lithium-ceramic battery materials for e-mobility with the construction of a gigafactory in Dunkirk, France
Arkema has been chosen by ProLogium, a Taiwanese technology leader in advanced batteries, as a key development and supply partner ahead of the launch of its gigafactory in France.
BASF invests in capacity expansion of Basoflux® range of paraffin inhibitors in Tarragona, Spain.
BASF Tarragona →Increased production at the BASF site in Tarragona, Spain to support growing global demand for high-quality paraffin inhibitor chemistries. Investment reinforces BASF’s commitment to innovative and...
LYB to build integrated plastic waste recycling hub in Chemiepark Knapsack, Germany
Chemiepark Knapsack →The hub is planned to combine various advanced sorting and recycling operations, helping to address the plastic waste challenge and grow the circular economy